![]() |
|||||||||||||||||
![]() |
|||||||||||||||||
intro | geology | gold & silver | gold | silver | mining@ martha | monitoring | noise | dust | earthworms | Education Centre | activity schedule | feedback The Mining Process Find It Dig It Crush It Treat It Manage the Waste Make the Water Clean as Clean Make it all Green Again
|
|||||||||||||||||
![]() above: Geologists sample the pit floor to define ore from waste rock. right: The open pit operates twelve hours a day, five and a half days a week. By 2007 the pit will be approximately 860 metres long, 600 metres wide and 250 metres deep. Ground water from around and beneath the pit is pumped out. Some of this water is used on site to wash vehicles and to spray the haul roads to dampen dust. Excess water is piped over to the Water Treatment Plant near the Processing Plant to be treated before it is discharged to the Ohinemuri River. |
2. Dig it. (Sampling, Assaying, Blasting, Mining, Dewatering) Material mined from the open pit is either ore (containing gold and silver) or waste rock (little or no gold and silver). To find out which is which, samples of rock are collected from surveyed lines (channels) along the ground. The samples are sent to an assay laboratory where the rock is tested for its gold content. Geologists (left) use the results to mark out the sampled areas on the pit floor into zones of ore and waste rock so they can be mined separately. Areas of hard rock need to be blasted to break it up before it is dug. Then it is excavated by backhoe diggers and loaded onto trucks. |
||||||||||||||||
![]() |
|||||||||||||||||
3. Crush it. (Crushing, Conveying, Stockpiling) There are two types of crushers used at the mine site. A jaw crusher breaks up the hardest rock and two feeder breakers deal with the softer material. They break the larger rocks to a size suitable for transport from the mine site. The rock is carried away from the open pit by a conveyor belt. Ore and waste rock travel on the same conveyor, but at different times of the day. Ore travels 1.7 kilometres to the stockpile at the Processing Plant. Waste rock travels 2.7 kilometres to the loadout near the waste rock embankments. About 30,000 50,000 tonnes of rock is carried on the conveyor belt each 12 hour day. This is enough to cover a whole rugby filed to a depth of one metre. The rock sometimes contains metal and timber from the old workings. This is called tramp material. The metal is picked up by electromagnets and the wood is taken off the conveyor belt by hand. below left: 85 tonne dump trucks tip ore and waste into the crusher. Ore and waste travel on the conveyor at separate times. |
|||||||||||||||||
![]() |
|||||||||||||||||
![]() |
|||||||||||||||||
![]() |
|||||||||||||||||
![]() |
|||||||||||||||||
above left: Ore travels 1.7 kilometres to the stockpile at the Processing Plant. Waste rock travels 2.7 kilometres to the loadout near the waste rock embankments. above right: Ore is stockpiled before being transported to the processing plant in the background. 4. Treat it. (Grinding and Sizing, Leaching and Adsorption, Elution and Electrowinning, Smelting and Pouring) Grinding and Sizing Ore processing is a 24-hour operation. A front-end loader feeds ore from the stockpile near the processing plant into a hopper. The ore falls down onto a conveyor belt and is fed into the SAG mill (semi-autogenous grinding mill) along with water, lime and hardened steel balls. |
|||||||||||||||||
![]() above: The hardened steel balls and ore inside the SAG mill. The balls are like athletics shot puts in various sizes. They become quite small after a few weeks of tumbling. This picture was taken during a maintenance shutdown. below: The slurry of ground ore, lime, water and cyanide is stirred through the leach tanks over a period of 24 hours.
|
The SAG mill is a large revolving drum. Rock is ground to a fine powder by the turning of the drum and impact from the hardened steel balls and the rock itself. A large sieve separates the oversize material and worn-down steel balls from the finer material. The oversize rock is returned to the SAG mill, worn-down steel balls are removed from the circuit with a magnet and the finely ground material is sent to the hydrocyclones. The hydrocyclones rapidly spin the ground rock to classify it into sizes. Larger particles are returned to the SAG mill or the second ball mill for further grinding. Material that has been ground small enough is sent through to the leach tanks. The slurry that remains after grinding is complete has a very fine particle size. The rock has been ground to the size of very fine beach sand (80% of the ore particles are less than 70 microns). ![]() Leaching and Adsorption The slurry of ground ore, water and lime moves through a series of tanks to which a weak solution of sodium cyanide is added. The gold and silver is dissolved by the cyanide solution, rather like sugar is dissolved by warm water. The slurry then passes into a series of adsorption tanks. These contain carbon granules. The carbon granules, about the size of chocolate hail and made from coconut shells, have been heated to 600 degrees Celsius. The gold and silver are attracted to the surface of the carbon. This is called adsorption. The carbon granules, loaded with gold and silver, are removed from the tanks. The barren slurry, now known as tailings, is pumped to the tailings storage facility. Elution and Electrowinning After the 'loaded' carbon is screened out of the tanks it is pumped to another tank, called an elution column, where gold and silver is washed off the carbon using superheated water. This forms a solution called loaded electrolyte. The used carbon is washed and reheated to 600 degrees Celsius. This makes it active again. The carbon is returned to the tanks for further adsorption. Smelting and Pouring |
||||||||||||||||
The bullion is sent to the Western Australian Mint in Perth, where it is further refined to separate the gold from the silver. Then it is sent to the international market to be sold. In 2001 approximately 112,000 oz of gold and 860,000 oz of silver were produced from around 1.3 million tonnes of ore. This is equivalent to about $NZ1.5 million worth of gold and silver per week. About 80% of the total revenue remains in New Zealand (as salaries and payment for goods and services). 5. Manage the waste. (Tailings, Waste rock) The two main waste materials that come from the Martha Mine operation are tailings and waste rock. Tailings is the name for the slurry that is left after gold and silver have been extracted from the crushed ore. Tailings slurry is made up of approximately 30% finely crushed solids and 70% water, including small amounts of cyanide that remain after processing the ore. Because tailings contain cyanide, it is important that they are managed carefully. Tailings are pumped to the top of the waste rock embankment and placed into a pond. Here, the fine solids settle and compact. The water in the tailings is decanted from the surface of the pond and sent back to the processing plant to be reused in the grinding circuit. In the tailings pond, cyanide in the water is rapidly broken down by sunlight into naturally-occurring carbon and nitrogen. Any seepage from the tailings pond is collected in an underdrainage system built within and below the embankments. |
|||||||||||||||||
![]() |
![]() |
||||||||||||||||
above: Tailings are pumped to the top of the waste rock embankment and placed into a pond. Here any residual cyanide degrades naturally on exposure to the ultra violet light in sunlight. left: The tailings pond and the waste rock embankment are together known as the Tailings Storage Facility. |
|||||||||||||||||
Waste rock is material from the open pit that doesnt have enough gold in it to make it worthwhile for processing to extract gold and silver. However, waste rock is very important as building material for the waste rock embankments of the Tailings Storage Facilities. In the Martha Mine open pit there are several types of waste rock. The various types must be sorted, mined separately and used in the most suitable places within the embankments. For instance, material known as ash is best used as a subsoil beneath topsoil and pasture; some types of rock are easily compacted and are best used as lining material. The diagram below shows the range of zones within the waste rock embankments. |
|||||||||||||||||
![]() |
|||||||||||||||||
Zone A: Lining material for the base of the waste rock embankment Zone B: Lining material for the upstream shoulder of the embankment Zone C: Helps to form a strong layer next to the upstream shoulder Zone D: Forms the bulk fill in the embankments Zone E: Similar to Zone D Zone F: Forms a layer between Zone D and Zone G Zone G: Forms a capping layer as a base for rehabilitation Zone H: The rehabilitation cover, or subsoil, that lies under the topsoil layer 6. Make the water clean as clean. (Water treatment, Chemical analysis and Flow monitoring, Biological monitoring) The Waihi area has a high rainfall and this means that there is more water on the mine site than is needed for the mining operation. Water that is not needed on site is discharged to the Ohinemuri River. There are strict controls over the quality of water that goes into the river. All water discharged from site must meet strict discharge standards and usually requires treatment at the Water Treatment Plant. There are four sources of water on the mine site: 1. Mine water is pumped from underground, beneath the open pit. 2. Stormwater runoff is collected in silt ponds and collection ponds around the site. 3. Decant water is collected from the surface of the tailings ponds. 4. Underdrainage water is collected from drains beneath the tailings ponds and waste rock embankments. Mine water and stormwater contain metals and trace ions that must be removed or reduced in the water treatment process. Decant water and underdrainage water contain cyanide that must be removed before being treated in the same way as mine water and stormwater. |
|||||||||||||||||
![]() above: The Water Treatment Plant treats water before discharge to the river. below: The Ohinemuri River is regularly monitored both by the company and independent bodies. ![]() |
Water Treatment Chemical Analysis and Water Flow Monitoring Samples are collected at various stages of the treatment process and sent to independent laboratories for analysis. The standards used for the quality of discharge water are based on the United States Environmental Protection Agency (USEPA) guidelines for the protection of aquatic life (where such appropriate limits exist, and other guidelines where appropriate). Water flows are also measured. The consents allow up to 20,000 cubic metres per day to be discharged from the Water Treatment Plant, or 15% of the river flow, whichever is the lesser. Biological Monitoring Baseline studies of the water quality and aquatic biology of the Ohinemuri River and its tributaries began in 1981. Monitoring is ongoing and is an important part of the treated water discharge consents. 7. Make it all green again. (Progressive rehabilitation, Open pit, Waste rock embankments, Other areas, The Martha Trust) Rehabilitate = renew, restore, convert, fix up, make good, rebuild This means planting trees, planting pasture and planning for the future. Progressive rehabilitation Some rehabilitation is ongoing while the mine is operating (until 2007). |
||||||||||||||||
Whenever activity in an area is complete, progressive rehabilitation takes place, establishing and building towards the long term rehabilitation plans. This can involve contouring final pit walls and waste rock embankments, planting pasture and creating areas of trees and shrubs. Progressive rehabilitation enables disturbed land to become productive as early as possible. It also provides a vegetation cover over areas where bare earthworks could otherwise cause erosion, dust and silt, as well as appearing unsightly. |
|||||||||||||||||
![]() |
![]() |
||||||||||||||||
above left: Previously mined areas are rehabilitated. Hydroseeding ensures a rapid growth of ground cover. above right: Young cattle graze on a section of the rehabilitated waste rock embankment. Final rehabilitation of the open pit Once mining is complete, the open pit will become a recreational lake with adjacent parklands. The open pit, 250 metres deep, will begin to fill with water in 2007 and it will take about five years to fill to a depth of 195 metres. The pit walls above the lake level will be planted, where possible, with trees and shrubs. Some areas of the lake will have shallow edges to form a lake shore and there will be a recreational area with boat ramp, picnic spots, amenities block, road and carpark. |
|||||||||||||||||
![]() |
|||||||||||||||||
left: An artist's impression of the proposed future pit lake development. Walking tracks and a recreational area can be seen next to the lake in the lower part of the picture. |
|||||||||||||||||
Final rehabilitation of the Waste Rock Embankments The land at the waste rock embankments will be returned to pasture, with pockets of native trees and shrubs. A wetland area will be created at the top of both embankments with pasture capping around it and a littoral zone of plants such as raupo, flax and cabbage trees between the pasture and the pond edge. Final rehabilitation of other areas Along the conveyor path and at the processing plant, buildings, equipment, structures and tanks will be dismantled and removed. The ground will be recontoured, replaced with pasture and planted with trees and shrubs. It is possible that the conveyor path could be developed as a walkway to link up with a network of other walks around the local area. |
|||||||||||||||||
![]() |
|||||||||||||||||
The Water Treatment Plant is expected to be in continued use for a time after the mine has closed. When it is no longer necessary it will be transferred to a Trust. The Martha Trust After mining stops at the Martha Mine, stages known as Closure and Post Closure begin. Closure is the period of final rehabilitation and finishes when the regulatory authorities consider the site has reached a 'safe, stable, self-sustaining, rehabilitated state'. The Post Closure period starts with the formation of the Martha Trust. The Trust will own, manage, monitor and maintain the land and facilities at the wetlands, Water Treatment Plant and the parklands adjacent to the lake. It will also be responsible for maintenance and monitoring of the lake. The Company will hand over a sum of money to the Trust. This money and the interest it earns will be used to carry out the responsibilities of the Trust in perpetuity. Key Concepts & Words Find It: Exploring, Investigating, Baseline monitoring, Permitting Dig It: Sampling, Assaying, Blasting, Mining, Dewatering Crush It: Crushing, Conveying, Stockpiling Treat It: Grinding and Sizing, Leaching and Adsorption, Elution and Electrowinning, Smelting and Pouring Manage the Waste: Tailings, Waste rock Make the Water Clean as Clean: Water treatment, Chemical analysis and Flow monitoring, Biological monitoring Make it all Green Again: Progressive rehabilitation, Open pit, Waste rock embankments, The Martha Trust LInks to other sections of the Martha Mine website For more detail on the mining process click here. Links to other sites For information on the proposed Favona underground mine see www.favona.co.nz For a range of educational material on gold and silver, including answers to the most often-asked questions about gold mining, see the section on precious metals on the New Zealand Minerals Industry Association website www.minerals.co.nz. Click here to go straight to the section.
Martha Mine Educational Resources for Schools [ RETURN TO TOP ] |
|||||||||||||||||