Color
timeline I the original Martha I the Victoria Battery | the Cornish Pumphouse | extracts from the past | Cornish Pumphouse on the move
Waihi's historic Cornish Pumphouse was ‘on the move’ in 2006!
The Cornish Pumphouse was built in 1904 to house steam-driven pumping machinery to dewater the underground Martha Mine that operated from the 1880s to 1952. The steam machinery was used until 1914, when it was replaced by electricity. During the 1930s the machinery was stripped out and the building became derelict.

Historic underground mine workings threatened the stability of ground beneath the pumphouse and investigations from 2004 concluded that the only way to protect the historic building was to relocate it to a safe site. In 2006 internal bracing was installed to strengthen the structure and earthworks were carried out to construct the relocation causeway.

In an acclaimed feat of engineering, this iconic building – weighing 1840 tonnes and standing three storeys high, was moved in its entirety to its present site during the third quarter of 2006. It was shifted on teflon-coated concrete beams to a new site 300 metres away.
Follow progress of this massive feat of engineering as it unfolded in the photo diary below...

The Cornish Pumphouse was built around 1904 to house steam-driven pumping machinery needed to dewater the mine.The pump was used until 1913 and kept in working order until 1929. After this it was abandoned, the machinery removed and the steel beams inside removed for scrap.
photo taken about 1950
In 1961 the collar of No. 5 shaft west of the pumphouse collapsed leaving the structure on the edge of a potentially dangerous void.
This aerial photograph taken from the south in the mid 1980s shows the collapsed No.5 shaft on the left (west) of the picture.
In 1987 Waihi Gold Mining Company fenced the area around No.5 shaft for public safety. Construction of Martha Mine had begun and a viewing platform was placed next to the pumphouse. Paths were constructed and the area planted with native trees and shrubs.
With the town's Information Centre and the Martha Mine Education Centre operating close to the pumphouse the area further developed as a significant tourist attraction.
The autumn colouring of the Virginia Creeper accentuates what had become a tourist icon.
By 1995 regular monitoring of the building and surrounding area by Waihi Gold Mining Company showed that the pumphouse was slowly tilting, and that the ground on which it was built was also moving.
In 1999 access to the pumphouse was restricted following a series of nearby ground subsidences and the increased danger of a similar subsidence of No.5 shaft immediately adjacent to the structure.
By the beginning of 2005 it was obvious that the pumphouse was tilting dangerously and the ground on which it sat was continuing to move. Experts advised that if it was to be saved the building itself would have to be moved. All interested parties met to consider the future of the structure. In June 2005 conservation architects responsible for moving the Museum Hotel in Wellington got a close look at the condition of the 100 year-old structure
June 2005
A 100 tonne capacity crane was brought on site to secure the weight of a small drill rig above the partially collapsed No.5 shaft. The rig drilled into the shaft to investigate ground conditions.
June 2005
A flat rack container platform supported the small drill rig above the partially filled No. 5 shaft. The platform was suspended from the crane. Staff wore fall arrest equipment attached to a rail above the platform.
June 2005
A large range of possible relocation sites and transport routes was considered. A geoprobe vehicle investigated the condition of the ground along which the pumphouse may travel. This information allowed geologists to determine how much preparation each section of the route would require.
December 2005
Scaffolding was installed inside the pumphouse ready for detailed investigations of the structure and the installation of internal steel beams to brace the building.
A final site and relocation route was determined. The pumphouse will first move south ( to the left of the picture) and then travel west along the tree line towards the top right of this photograph.
January 2006
Pine trees along the selected transport route were removed.
30 January 2006
All trees and undergrowth removed. The site was ready for earthworks to commence once archaeological inspections were complete.
31 January 2006
Upper level steel work was welded at Mount Maunganui Engineering's workshop.
far left: 31 January 2006
Lower level beams were completed at Mount Maunganui and transported to Waihi

left: 2 February 2006
A small selection of the bottles found by Ray Hooker during archaeological investigations.

2 February 2006
Consulting archaeologist Ray Hooker unearthed a bottle dump just west of the pumphouse.
12 February 2006
Ray Hooker shows local members of Historic Places Trust a small selection of the artifacts he has collected. All artifacts were catalogued and recorded. Over a period of two weeks over 250 people took advantage of the opportunity to take guided tours of the site and see the pumphouse close up for the first time in many years.
The condition of the structure was regularly photographed and logged.
14 February 2006
Lower level beams were welded into place.
23 February 2006
Upper level steelwork was bolted into place. These beams provided the internal support for the shell of the structure during the move and remain in place in the new location.
3 March 2006
Weak ground to the south of the pumphouse was removed to reveal the building's original foundations. Underdrains were installed in the area and then it was refilled with competent material capable of supporting the pumphouse for its 'step out' 26.5 metres to the south before beginning its journey approximately 300 metres west to its new home.
3 March 2006
The orginal pumphouse foundations. Five foundation shafts were dug, timbered and then filled with concrete to provide the base on which to build the pumphouse. Some of the original timbers can be seen. The pumphouse was cut from these foundations just above the timbers.
12 March 2006
Preparations continued on the route the pumphouse will take. Several weeks of fine weather meant the project was progressing well.
13 March 2006
Rafters were lifted into place from the north side. On the skyline the pumphouse now looked the same as it did over fifty years ago in the photo at the top of this page.
14 March 2006
With the rafters in place the steelwork paint was given a final touch up and the upper level of the scaffolding was removed.
14 March 2006
Looking as good as new. Rafters, steelwork and beams were all modelled on the originals to preserve the integrity of the building.
23 March 2006
The ground level to the south of the pumphouse was built back up to its orginal level using material capable of holding the weight of the building during its move.
24 March 2006
Attendees at the 2006 Annual Miners' Reunion got a close up view of activities on site
.
5 April 2006
Preload was added to the south of the pumphouse. This material acted as a weight to compress the ground ready for the move. It was removed after measurements confirmed that the route had been compressed sufficiently to hold the almost 2000 tonne weight of the building during transportation.
13 April 2006
The pumphouse was illuminated as part of Waihi's celebration of 100 Years of Rail over Easter weekend. Preload material is silhouetted in the lower foreground.
21 April 2006
With scaffolding now removed from the lower level a small excavator was used inside the pumphouse to remove soil and debris from the lower floor under the watchful eye of archaeologist Ray Hooker.
9 May 2006
How do you begin to chop a pumphouse off its base? With a very big saw, in this case a diamond-tipped circular saw that is reputed to be the biggest in Australasia. At a later stage of the operation a diamond wire saw will be used.
25 May 2006
Autumn rains slowed progress. The 'step out' pad was constucted to the south of the pumphouse. Compare this picture to those above taken on 3 March 2006 .
2 June 2006
As work nears completion on the 'step out' pad, an excavator prepares the causeway adjacent to the old Royal Filling Shaft. Early morning sun through low lying mist silhouettes the machinery and the pumphouse.
8 June 2006
The first two tunnels were cut through the base of the pumphouse. Boxing was constructed to cast the first two slider beams in situ. Once these were in place the next tunnels were cut and the remaining three beams constructed.
14 June 2006
A view from inside the pumphouse looking south. Steel reinforcing for the slider beam is in place. The cut line for the next tunnel can be seen below the leg of the contractor who is working in the area where the flat jacks will be placed to lift the building.
19 June 2006
Meanwhile the new site for the pumphouse has been prepared. The white dots superimposed on the picture show the building's new position. To the right is Seddon Street and the historic Anglican Church that celebrated its centenary later in 2006. The replica poppet head on Upper Seddon Street is obscured by trees in the background.
22 June 2006
The first two slider beams were poured. A fleet of trucks provided the concrete that was pumped across the site and poured into the boxing, then smoothed off to a tolerance of plus/minus 3 millimetres.
4 July 2006
The bottom section of the pumphouse was clamped together using threaded stress bars that were screwed up tight. More internal bracing was added at the lower level.This held everything firmly in place during the move. In the foreground is the steelwork for slider beam #1, ready to move into position next to beam #2 that has already been poured.
10 July 2006
It may not look much, but this is the diamond wire saw in action. The machine in the foreground powers the wire which acts much like a cheesecutter. Here the north wall tunnel for slider beam #5 is cut through from inside the pumphouse. Later, when the weight of the pumphouse was supported on all five slider beams, the same machine completed the final cuts and separated the building from its foundations.
21 July 2006
While work continued on the pumphouse in the background, in the foreground the precast concrete slider beams were placed on the causeway in readiness for the move. The pumphouse passed over these beams which were then reused and 'leapfrogged' down the transport route ahead of the building by passing them through a trench in the causeway under the pumphouse.
27 July 2006
This aerial photo clearly shows the 'step out' route and the change point where the tilt and orientation of the pumphouse were corrected before the building was jacked along the causeway.
7 August 2006
On the move!
At 6.30am the building began its epic journey. Four large hydraulic rams pushed the building. At the left staff can be seen controlling the valves that adjusted the speed and direction.
9 August 2006
Time lapse photography shows progress. By the end of the first week the pumphouse had moved 22 metres - almost to the end of the ‘step out’.
14 August 2006
By the end of the first week the pumphouse had moved just over 22 metres along the 26 metre step out path and was almost ready to turn slightly in preparation for the journey west. During the week the building featured on TV 1 and TV 3 news, and in many newspapers. A new viewing platform on upper Seddon Street provided a great view for the public.
17 August 2006
The pumphouse completed its step out and the western end (furthest from camera) was rotated to the south (left of picture) to align the building with the causeway. One ram was moved from the north wall to the east wall to assist with the rotation.
25 August 2006
Both rams were moved to the west of the building to pull the pumphouse.

1. concrete slider beam, 2. mild steel covered with stainless steel, 3. teflon pad, 4. flat jacks, 5, bracket system, 6. pumphouse concrete.
5 September 2006
Far Left: Teflon pads.

Left: After the pumphouse had moved over the slider beams the back beams were unbolted and jacked to the middle trench under the building. Then they were winched on rollers to the front, jacked into position and reinstalled.
12 September 2006
The first slider beams can be seen here jacked to the middle of the track where they are pulled under the pumphouse and placed in front of the structure.
16 September 2006
About one third of the distance had been covered. As the pumphouse got nearer to town it was easier for members of the public to get a good view from the viewing areas specially set up.
20 September 2006
Staff from the Waihi Information Centre watch from a public viewing area. They are wearing hardhats and hi viz in readiness for a site visit.
2 October 2006
Keen as always to assist wherever possible, the Waihi Lions Club lent a hand on a Sunday when the regular crew are not at work. The club is on the lookout for new members and used the photo opportunity provided by the pumphouse move to get this attention grabbing image. Only about 160 metres to go!
17 October 2006
Getting closer ...
24 October 2006
... and closer ...
Only three beam moves to go!
27 October 2006
A different view taken from the western viewing platform looking south to the pumphouse as it moves behind the current pit rim. The picture shows the approximate original and final positions at the left and right of the frame.
3 November 2006
Almost there! The pumphouse was now abnle to be clearly seen from the main street of Waihi, making an imposing sight at night.
8 November 2006
The last few metres
8 November 2006
Just before sunset Newmont Waihi Gold general manager Adriaan van Kersen and Golden Legacy Centre manager Doreen McLeod cut the ribbon to celebrate the building's arrival.
8 November 2006
The 'grand old lady' settles in for her first night in her new location, three months and one day after setting out.
3 February 2007
Welcome Home! Prime Minister Helen Clark and over 750 other guests gathered on site to officially welcome the pumphouse to its new home. Several hundred people also watched the proceedings on a large screen set up nearby.

‘On the Move’ - A DVD of the relocation project and a book of photographs were produced and are available for purchase. For more information email: linda.willoughby@newmont.com
[index | gold & silver | history I geology I mining @ Martha I rehabilitation I safety health environment I Martha & the community | economics & employment | tech info | what's new? I links to other sites I glossary ]

[ RETURN TO TOP ]