Earthworms - Science-in-Action

Worms

When we carry out wormseeding, sods of earth from fertile paddocks are placed on measured spots on newly rehabilitated pasture along with a dash of lime. Before long the worms start doing what worms do and the quality of the new pasture improves.

At Baxters Road, on the waste rock embankments, completed construction areas are covered in top soil and subsoil and then grassed, fertilised and grazed - but the new pasture doesn't contain many worms. In other areas around the site, more established paddocks have numerous worm populations.

The worms have benefited this pasture by aerating the soil, distributing nutrients throughout it and mixing up the soil layers. At the mine the first worm seeding exercise was in 1992. Over the years, as rehabilitated pasture is ready, sections are seeded with worms. The local primary schools have been involved from the start, recognising this is a worthwhile science-in-action learning experience for the students. They carry out classroom activities before and after their visit to the mine site and build their own worm farms at school. This year 193 students from five schools took part.

The children found out that a sod of earth contains, on average, ten worms. That converts to 160 worms per square metre and 1.6 million worms per hectare. They also discovered that there are 173 native worm species in NZ, the longest species can grow up to 1.3 metres long, an earthworm has five hearts and they can live for up to eight years.

 

Eastern Layback

This is an update on what is happening about the proposal to lay back the east wall of the Martha Mine open pit. We are continuing to work on internal processes to further the proposal. At the moment there is little progress to report.

What has happened up to now?

Investigations to assess the feasibility of laying back the eastern wall of the Martha Mine open pit began in 2007. Along with the cancelled western layback proposal, the potential for an east layback was raised and discussed with residents and community groups.

A drilling programme, geological modelling and economic investigations were undertaken. A draft business case for the east layback proposal was established and the proposal began its path through the Stage Gate process. The Gate Three meeting is to take place in October.

Progress from there focuses on confirming the refined pit configuration and verifying that the capital should be invested in the project.

The proposal:
If it goes ahead, the East Layback will be similar in construction to the current South Wall Stability Cutback (SSC), but will be smaller. It will extend the Martha Mine's life until 2012 as outlined in the 'Operating Scenarios' timeline developed and communicated over the last 12 months. The latest version of the timeline is available.

The scope of the proposed project means that operations would remain within the existing Grey Street noise bund. Operations would appear no different or with very little difference and effects are likely to be similar to those from the existing open pit mine. Rehabilitation and pit wall stability work would continue to be ongoing throughout the layback project.

NWG will continue to keep residents and the wider community informed of the internal and regulatory processes required to obtain the go-ahead for the East Layback proposal, and its progress. If you would like to find out more please call our community engagement phone 0800 NEWMONT (0800 639 6668).

Walkways Weed Spraying

From time to time during September and October Glyphosate and Brushkiller weed spray (with associated penetrants, surfactants and maker dies) will be used to control weeds on and around the walkways associated with the Martha Mine pit rim and the Black Hill Reserve, Waihi. For further information please contact: Mark Samson, Sustainability Manager, 07 863 8192

 

Stocking Up On Ore

Newmont Waihi Gold has had an application approved to slightly increase the capacity of the polishing pond ore stockpile. This was originally consented in April 2004 and has been used since October 2006.

The polishing pond stockpile is adjacent to the water treatment plant and mill at the Baxter Road site. It stores ore from the Martha Mine open pit. Under routine operating conditions the ore is fed from the stockpile into the mill for a few days while the mill is processing rock from Martha. Then the stockpile is replenished with ore from the open pit while the mill is on a Favona campaign.

The fire at the mill motor control centre on 5 May this year shut down ore processing until the end of July. Newmont chose to continue mining, even though at a reduced rate at the Martha Mine, to avoid having to lay off Macmahon staff for the duration of the shut down.

Now that processing of ore has restarted priority is being given to the higher-grade Favona ore that has accumulated during the shut down. In the meantime, the quantity of Martha ore will continue to grow, requiring an extension to the polishing pond stockpile.

The consented design currently in use has a footprint of 5.1 hectares, a height of 30 metres and a maximum capacity of 1.4 million tonnes. The approved extension has a smaller footprint of 4.6 hectares and a height of 35 metres, which increases capacity to 1.5 million tonnes.

Location of the polishing pond stockpile

The aerial photograph shows the location of the polishing pond stockpile.

The revised design can be built in accordance with and operated within the scope of the existing consents where they relate to matters such as hours of work and operating noise limits. However, some minor variations have been approved relating to the stockpile liner and collection pond liner. It is expected to take three months to complete the construction work.

It is unlikely that residential properties will experience any increase in noise effects as all construction and operating activities will occur below the level of the Moore Street noise bund.

The visual effect of the extra five metres of stockpile height will also be minimal because native vegetation planted by Newmont along Golden Valley Road provides effective screening.

For further information please contact Kevin Storer on 07 863 8192