Drill Bits

Drill rigs are currently working near Union Hill, in Moresby Avenue and near Waihi Gold's mill. An opportunity to have a close look at what happens on a drill rig is offered to members of the public. It is essential to book a place on a drill rig visit as numbers are limited and high-viz safety clothing is supplied.

Please phone Jeannine or Guy 07 863 9880 if you would like to book a visit or if you would like more information.

Pit Rim Walkway Reopened

Over the last few weeks the pit rim walkway between the western viewing platform and Martha Street has been closed while drilling rigs were operating there. Now drilling in that location is complete and the walkway reopened last week - just in time for the school holidays.


The Newmont Waihi Gold freephone is attended 24 hours a day, seven days a week.


0800 NEWMONT (0800 639 6668)

Here's the idea... Tell us what you think

Newmont Waihi Gold is currently seeking community opinion about new proposals to continue activity in the Martha open pit after the southern stability cutback is complete in 2010.

The company is airing a concept to lay back the walls of the open pit at the east and the west. At this time we emphasise that this is a concept. There is no project.

For this concept to be feasible and for consent applications to proceed, Newmont Waihi Gold will need to be satisfied there is broad community support and favourable outcomes from the technical studies and drilling programme.

Newmont Waihi Gold is seeking a win/win situation for both the community and the company. There must be benefit for both if the Martha layback proposals go ahead. Therefore it is important to begin considering what options and opportunities may be presented in order to work towards achieving positive outcomes, as well as taking on board any effects the laybacks may have on the community.

East Layback

The exploration drilling programme within the open pit at the eastern side ran from February to June this year and is due to resume soon.

If the eastern pit layback proposal becomes more than a concept, excavation will remove material from the 'Milking Cow', an area known to be unstable due to historic underground workings. This is a potential long term solution to an issue highlighted in 2002 when a geotechnical report identified hazard zones there.

If a layback to the east goes ahead activity is expected to take place within the current noise bund and within the current mining licence boundary, which will remain unchanged in the east.

It is expected that there will be little change from present activity except that it will continue for longer.

West Layback

The exploration drilling programme at the western side began in June this year. Initially drill rigs were working within the open pit and then were moved to different sections of the pit rim walkway and to an area on Moresby Avenue adjacent to Waihi Central School and the Goat Track.

The programme is due to finish soon, with two rigs currently operating between the walkway and the road. These drill sites are marked on the photograph below. If a layback to the west proves feasible, considerable work on avoiding or mitigating potential effects will be necessary, particularly for Waihi Central School.

The school and the company will be working together over the next few months to consider the issues and achieve the best possible outcomes.

The proposed western layback will alter the shape and height of the western pit wall. This provides an opportunity for new rehabilitation options to be introduced and considered. A park, plantings and lake access from Moresby Avenue, for instance, could have features worth developing.

West Veins

In this aerial photograph showing the western perimeter of the open pit the known vein systems are shown in black and the locations of drill sites are shown as white dots. This differs slightly from a similar image published in 'Update' June 26, which indicated proposed drill sites. Not all of those were drilled.

West End

Quartz veins of interest within the western wall of the open pit are outlined on this photograph.

Timing?

Currently operations in the open pit are concentrated on the southern stability cutback. This work will be finished by mid 2010. If one or both of the proposed Martha laybacks are to proceed it would be desirable for work to begin in 2010 so continuity of employment could be assured. A western layback could take around 18 months to two years to complete. Ideally an eastern layback would follow and could also take about two years to complete.

It will take a considerable time to gain all the necessary consents. In order to meet the 2010 deadline the company will make a decision in early 2008 on whether to proceed to the next phase.

Newmont Waihi Gold expects that results from the exploration drilling programme and also the specialist technical studies will be available early in 2008. In the meantime the company is seeking community feedback. All factors will then be assessed and a decision will be made about whether to go ahead with a full consenting process.


More Information

At the moment we don't have a lot of information and detail to offer. We will be pleased to come and talk to community groups and bring along more information as it comes to hand.

To arrange a visit or if you have any questions please contact our Company Liaison Officer, Donna Fisher. Phone 0800 NEWMONT (0800 639 6668)

In further 'Updates' over the next few weeks and months we will provide more detail about the layback proposals.

PM Visit

Prime Minister Helen Clark and VWT CEO Eddie Morrow

Prime Minister Helen Clark is very pleased to have the 'On the Move' book and DVD set, presented to her by Eddie Morrow, CEO Vision Waihi Trust. As Minister for Arts, Culture and Heritage, the Prime Minister has a special interest in Waihi's Cornish Pumphouse.